Approved Capital Improvement Projects
2022
Approved Capital Project Expected Cost
Jordan #29 - Replace 3,800' pipe $60,000
Lancaster #10 - Replace 2,200' pipe  $15,000
Lyon #32 - Replace 2,000' pipe $45,000
Tibbling #14 - Replace 1,300' pipe $40,000
Replace Waterboxes $30,000
SCADA Radio System $80,000
No. 3 Flume Replacement & Canal Improvements $6,000,000
2023
Approved Capital Projects Expected Cost
Jordan #29 - Replace 3,800' pipe (not completed in 2022) $60,000
Lyon #32 - Replace 2,000' pipe (not completed in 2022) $45,000
Tibbling #14 - Replace 1,300' pipe (not completed in 2022) $40,000
Replace Waterboxes (not completed in 2022) $30,000
No. 3 Flume Replacement and Canal Improvement $690,000
Office Equipment $15,000
District House Repairs $30,000
1/2 Ton 2WD Standard Cab Pickup $32,000
2024
Capital Projects Expected Cost
No. 3 Adjustments for Added Pressure $80,000
Jordan #29 - Replace 3,800' pipe (not completed in 2023) $60,000
Tibbling #14 - Replace 1,300' pipe (not completed in 2023) $40,000
Replace Waterboxes (not completed in 2023) $30,000
Office Equipment $15,000
District House Repairs (not completed in 2023) $30,000
1/2 Ton 2WD Standard Cab Pickup (not purchased in 2023) $32,000
Awarded Projects
2021
Vendor Award Date Purpose Contract
Krah USA 10/1/2021 Pipe and fittings for No. 3 Flume Replacement Project $1,650,269.50
Tapani, Inc. 12/10/2021 Removal of No. 3 flume and construction & installation of 2.5 miles irrigation pipe. $3,998,400.00
2022
Vendor Award Date Purpose Contract
Duke's Equipment and Parts LLC,   10/2022  Canal bank repair $1,441.77
2023
Vendor Award Date Purpose Contract
Greenwalt Electric LLC 10/23/23 Install power on screen $4,429.19
Alliant Communications 3/31/23 Upgrade (1) Desktop Computer $2,305.59
Copiers Northwest 3/31/23 Replace Copy Machine $5,827.62
2024
Vendor Award Date Purpose Contract
Selland Construction, Inc.    02/2024 Tunnel No. 9 Repair $177,800.00